Hansa Flex factory
Electrical installation for the 600 m² Hansa Flex production workshop in Varketili, Tbilisi: cable network design, 140 m of cable trays suspended on steel wires, cable pulling, Legrand Plexo sockets and switches, assembly and installation of a 110 kW main switchboard, power connection of machine tools. Completed in 28 days, December 2024 – January 2025.
- Area, m²
- 600
- Power, kW
- 110
- Switchboards
- 1
- Cable trays, m
- 140
- Duration, days
- 28
Scope of work
- Main switchboard
- Cable trays
- Electrical measurements
- Low-voltage networks
- Sockets and switches
Brands
ABB, IEK, WAGO, Phoenix Contact, Legrand